邻近隧道施工既有桥桩变形控制及注浆加固方案优化

来源期刊:中南大学学报(自然科学版)2014年第7期

论文作者:凌同华 张胜 李升冉 邓杰夫

文章页码:2394 - 2401

关键词:小净距隧道;桥桩变形;注浆加固;数值计算

Key words:neighborhood tunnel; deformation of bridge piles; grouting reinforcement; numerical calculation

摘    要:为了分析隧道在已有桥桩附近施工时对桥桩产生的影响,依托深圳市葵坝路隧道下穿高速公路桥梁段,采用三维有限差分法研究隧道动态施工引起的地表沉降以及桥梁桩基变形的规律,将数值模拟结果与现场监测结果进行对比分析,验证本文方法的正确性和有效性。为了进一步得到控制地表沉降和桥桩变形的最优注浆加固方案,通过改变注浆范围提出不进行注浆加固、原注浆加固以及优化后的注浆加固3种方案,并对这3种加固方案下地表沉降和桥桩变形进行对比分析。研究结果表明:优化后的注浆加固方案不但能够有效控制地表沉降和桥桩位移,而且能减小注浆范围,是最佳注浆加固方案。

Abstract: To study the effect of tunnel construction on the existing bridge piles, the settlement of strata and bridge piles deformation caused by tunnel construction were investigated by using three-dimensional finite difference method. Taking Kuiba Road Tunnel which traverses highway bridge piles in Shenzhen as research background, the correctness and validity of the method were verified by comparing the numerical simulation results with the in-situ monitoring results. To obtain the optimal grouting reinforcement scheme of controlling the settlement of strata and bridge piles deformation, three different schemes were proposed by changing the grouting range, such as without grouting reinforcement, the original grouting reinforcement and optimized grouting reinforcement. The settlement of strata around piles and bridge piles deformation using the three schemes of grouting reinforcement were compared and analyzed. The results show that the optimized grouting reinforcement scheme not only can control the settlement of strata and bridge piles deformation, but also decrease the grouting range, and therefore it is the best grouting reinforcement scheme.

有色金属在线官网  |   会议  |   在线投稿  |   购买纸书  |   科技图书馆

中南大学出版社 技术支持 版权声明   电话:0731-88830515 88830516   传真:0731-88710482   Email:administrator@cnnmol.com

互联网出版许可证:(署)网出证(京)字第342号   京ICP备17050991号-6      京公网安备11010802042557号